Claim: A steward of the former ruling Weah’s administration asserts that his government did up to 85% of the Ganta to Saclapea road.
Verdict: Misleading. Data from the Ministry of Public Works and the World Bank show that less than 85% of the roads were completed by the end of George Weah’s administration.
Full Text
The Chief of Staff in the office of former President George Weah has called on the Boakai administration to give credit to the Weah administration for the construction of portions of the road leading from Nimba to Grand Gedeh County.
According to Eugene Nagbe, the evidence is there that they conceived the idea of constructing the road, found the funding for it and did the actual initial civil work before leaving power.
He claimed that about 85% of the Ganta-to-Saclepea corridor had already been completed before the Weah administration left office.
Nagbe can be heard from 57:32 to 57:51 of a live talk show on Spoon FM.
To promote truth in the information ecosystem, DUBAWA verified the chief of staff’s assertion.
Verification
In her January 18, 2024, exit press conference, the former minister of the Ministry of Public Works outlined the status of the Ganta-to-Saclapea corridor.
As of the last day of December 2023, just 22 days before the Weah government left office, Ruth Collins said about 20 kilometres of the 39-kilometre Ganta to Saclapea road was asphalt.
This represents about 51% of the road being done by the Weah government, contrary to Eugene Nagbe’s 85% assertion.
Collins can be heard from 13:17 to 14:35 in her press engagement.
The World Bank, which Ruth Collins named as one of the funders of the Ganta to Saclapea road, also reported in June 2025 that only 48% of the corridor had been completed.
Conclusion
Eugene Nagbe’s claim, therefore, that the Weah administration did up to 85% of the Ganta to Saclepea road, is misleading.

<recruitement form="" is="" out="" we="" are="" replacing="" a="" new="" officers="" interested="" awpplicant="" should="" contact="" us="" for="" more="" informationICustom Auctions Is Up Again and Granting Nigerians the
Privilege to Own Vehicles at Affordable Rates
RICE AVAILABLE FOR SALES ARE :
Royal umbrella=18,000
Mama Gold=20,000
Royal stallion=18,000
Rising sun=18,000
Special rice=18,000
Mama Africa=18,000
Elephant Gold=18,000
Caprice =20,000
Gallon of oil =9,500
NOTE: TRANSPORTATION CHARGES IS (#1000) which must be paid before we ensure your delivery.
~INDUSTRIAL SEWING MACHINES
Toyota Land Cruiser-N1.3m TO N12.5 m
• Toyota Prado 850K TO N10m
• Toyota C o r o lla 500k TO N5.6m
• Toyota Camry 800k TO N7.2M
Spider 2million
Muscle N2.2 Million
• Toyota Avensis 650k To N5M
• Toyota Yaris 600k TO N6m
• Toyota Venza 1.7m TO N8m
• Toyota RAV4 SUV 700k TO N6.5m
• Toyota Hilus Pickup 950k TO N9m
• Toyota Dyna Truck 700k To N5m
• Toyota Hiace Bus 900k To N6.3 m
Hilux 900k TO 8m
* Toyota Highlander980k TO N12m
*Toyota Big daddy-N1.m
Tacoma 1Million TO 15m
Tundra 1.2m TO 16m
*Toyota Sinner 1.2m
many more…
Mercedes benze GLE 450 10.6m
Mercedes benze GLA 7.8m
Mercedes benze GLK 5.6m
many more…
Mercedes Benz ML330 1.850,000
Mercedes Benz ML350 2.8m
Mecedes Benz GLK 4MILLION
Mecedes Benz GLE 350 6M
GLE450 8M
GLA 250 3.8M
C class 2.9m
E-Class 3Million
Lexus Rx300=N800,000. To N2.1 Million
Lexus Rx330=N850,000 To N2.2 Million
Lexus Rx350=N900,000 To N4.3 Million
Lexus Rx470=N2.9m
Lexus es350 3.8m
Lexus Es330 2.6m
GX460 4m
Gx470. 4.3Million
Is250 1.8m
Nissan Altima 700,000
Nissan Murano 800,000
And many more…..
Range Rover Velar 9m
Range Rover vogue 8.6m
Land Rover 5.5m
And many more…
CONTACT (Officer GABRIEL ESHIEMOMOH )
O✓8✓0✓6✓7✓3✓9✓9✓0✓9✓0 W E DELIVER TO 36 STATES
NOTE ~ VEHICLES ARESLIGHTLY NEGOTIABLE.. INSTALLMENTAL PAYMENT IS FULL ALLOWED WITH A MINIMUM 4 MONTHS AND A MAXIMUM PERIOD OF 9 MONTHS… SHIPPING 100% UPON ORDER..